Government Schemes and Policy · 15 November 2026
Chennai Metro Phase 2: TBM Kurinji finishes 1.08 km tunnel between Kolathur and Srinivasa Nagar on Corridor 5
Exam-focused facts from the 15 November 2026 current affairs briefing.
Key facts
- Tunnel boring machine Kurinji achieved breakthrough at the north shaft of Srinivasa Nagar Metro Station on November 13, 2026, completing a 1,080-metre tunnel drive that began from Kolathur Metro Station on November 27, 2025.
- The completed tunnel is part of Corridor 5 of the Chennai Metro Phase 2 project, being developed to connect Madhavaram and Sholinganallur.
- The Madhavaram–Sholinganallur corridor is 47 km long, comprising 5.8 km of underground and 41.2 km of elevated sections.
- The underground construction package of the corridor includes five Metro stations and two ramps.
- TBM Kurinji navigated a sharp curve of 230-metre radius through soil, head rock and weathered rock, passing more than 70 borewells and open wells, without disrupting the public or road traffic.
- Tata Projects Limited is executing the underground work under Package C5UG06 on Corridor 5, with funding assistance from the Japan International Cooperation Agency (JICA).
- A total of 3.78 km of tunnel has been completed on Corridor 5.
- The tunnel boring machines deployed on the project are Kurinji, Marutham, Mullai and Neithal.