Science, Discovery, Tech and Environment · 18 November 2026

Bangladesh’s First Nuclear Power Plant at Rooppur Begins Supplying Electricity to National Grid

Exam-focused facts from the 18 November 2026 current affairs briefing.

Key facts

  • Bangladesh's first nuclear power plant at Rooppur in Pabna district began supplying electricity to the national grid on a trial basis on November 17, 2026, with Unit 1 initially supplying 350 MW.
  • The 2,400 MW Russian-assisted plant has two units of 1,200 MW each and is expected to meet more than 10% of Bangladesh's electricity demand once fully operational.
  • With the plant's connection, Bangladesh became the 33rd country in the world to produce and generate nuclear power.
  • The initial grid connection would last 8-10 hours for tests on the turbine, generator and grid stability, followed by disconnection and reconnection after about 28 hours for another 4-6 hours of operational checks.
  • Under the agreement with the Russian contractor, Unit 1 will undergo a 10-month trial operation before commercial generation at full capacity.
  • Construction began in 2017 during Sheikh Hasina's administration, following a 2015 agreement with Moscow.