Miscellaneous Current Affairs · 22 September 2026
Assam Chief Minister Lays Foundation for Adani's 3,200 MW Thermal Plant at Chapar
Exam-focused facts from the 22 September 2026 current affairs briefing.
Key facts
- Assam Chief Minister Himanta Biswa Sarma laid the foundation stone for Adani Power's 3,200 MW ultra-supercritical thermal power plant at Chapar in Dhubri district on Sunday, September 20, 2026.
- The ₹48,000 crore Chapar project is part of Adani group's ₹63,000 crore investment in Assam and is expected to generate 5,000 jobs.
- The plant, the largest power generation asset in the Northeast, will comprise four 800 MW units and be commissioned in phases from December 2030.
- Of the total investment, ₹15,000 crore is earmarked for two pumped storage plants with a combined capacity of 2,700 MW.